Appendix: Causes of Launch Delays
Sourcing Delays
Satellite Availability
The design, development, manufacture, and test timeline of a satellite is a complex endeavor, typically requiring years and often taking longer (sometimes much longer) than planned. The first new satellites for constellations are exposed to such delay risks. Once design and production processes mature, delay risks typically diminish but are not eliminated. Delays are quite possible, given that providing satellite-based global Internet services is a relatively new technology. For example, on May 1, 2018, OneWeb announced that its first 10 operational satellites, previously planned for launch that month, had slipped to the end of the year.38
Ground System Availability
The ground system required for the orbiting satellite constellation is also a source of delay risk. A recent example is the delay to deployment of GPS III satellites due to delays in completing the GPS III ground system.39,40
Launch Vehicle Availability
Like satellites, the development and production of launch vehicles can also lead to delays. The likelihood of a delay and the magnitude of the delay are both typically greatest for the maiden launch. Launch vehicle production can be impacted by natural disasters near or at the production facilities. Metrics on annual flight rates by launch service providers, both domestic and international, for the past several years show that any given provider has a relatively stable flight rate to meet its existing demand. These providers’ production lines are based upon the expected launch rate and will take time to ramp up.
The addition of hundreds of launches to propel thousands of satellites into orbit over the next several years seems likely to intensify delays due to a potential lack of launch vehicle availability. It is also possible that the price of launch services will increase if demand significantly exceeds supply.
Transportation
Accidents and delays happen in all modes of transportation. During the space shuttle era, a train carrying solid rocket motor segments from Utah to Florida derailed and an external tank being barged from New Orleans to Cape Canaveral was nearly lost at sea during a tropical storm.41 The Delta Mariner, a ship designed for carrying rockets from Alabama to Florida, collided with a bridge while proceeding in the wrong river channel at night. Satellites are also at risk. For example, damage during shipment of Superbird 8/DNS 1 to its launch site caused a nearly two-year delay.42
Regulatory
The licensing process for launch vehicles and satellites can result in launch delays. The Secretary of Commerce has stated that the current process for gaining regulatory approvals can take longer than the design-to-launch process. The National Space Council and the U.S. Department of Commerce are working to streamline the regulatory process to mitigate future delay risk.43
Launching on foreign soil does not free U.S. satellite operators from U.S. regulatory oversight and the delays that might result from such oversight and review. After a satellite is separated from their launch vehicle, satellite operators must adhere to the policies of their country of origin or registration, not the country from which they are launched.44
Launch Site Delays
Launch Vehicle and Satellite Processing
Activities during launch processing campaigns for both the launch vehicle and spacecraft can be delayed for any number of reasons. Individual tasks may take longer than planned. Problems or accidents during processing may occur. An issue with flight hardware may be discovered prompting a recall.45 Delays can occur when transferring flight hardware elements from one processing site to another (e.g., from an integration facility to a launch pad) due to weather or other causes. Labor disputes may result in the processing workforce going on strike or social unrest in the local area may cause a halt in operations.46,47
Launch Provider Capacity
The limited capacity of launch site processing infrastructure contributes to delay risk. Integration facilities may only be able to handle serial processing of one rocket at a time. The facilities’ processing capacity limitations consequently become production bottlenecks to higher launch rates and limit a launch service provider’s ability to catch up after a delay. Likewise, all launch pads can handle only one rocket at a time and require several days after a launch for refurbishment before they can accommodate the next launch.
A related launch provider capacity limitation stems from environmental concerns. Providers are required by the National Environmental Policy Act (NEPA) of 1969, 42 United States Code (U.S.C.) §§4321–4347 (as amended) to conduct environmental assessments to determine potential harm to the environment and public from their launch operations. These assessments are based in part on a maximum number of launches per year specified by the proposing launch service provider. The SpaceX environmental assessment for SLC-40 at Cape Canaveral Air Force Station (CCAFS) specifies 12 flights per year.48 Kennedy Space Center’s LC-39 consists of two launch pads (39A for SpaceX Falcon launches and 39B for NASA’s SLS) allowing up to two launches per month and up to 24 launches per year, but these numbers include non-SpaceX launches as well.49 At Vandenberg Air Force Base (VAFB) in California, the SpaceX assessment for SLC-4E cites 10 launches per year.50 The yet-to-be-built SpaceX launch complex in Texas cites 12 launches per year.51 The environmental assessment for Blue Origin’s New Glenn rocket allows 12 launches per year at CCAFS.52 The limits specified in these assessments may become a source of delay to constellation deployment. However, the government enforcement mechanism for these cited maximum launch rates is unclear. NEPA is subject to a citizen suit provision, meaning anyone can bring a lawsuit against the responsible federal agency for alleged NEPA violations.53
Current U.S. environmental assessments for rocket launch operations do not require consideration of atmospheric effects of rocket exhaust emissions above 3,000 feet. However, concerns regarding such emissions coupled with a large increase in launch rate could prompt new regulations and specify additional limits on launch frequency, further delaying constellation deployments. Scientists are beginning to explore this concern and the United Nations 2018 Quadrennial Global Ozone Assessment will include a section focused on rocket emissions.54 “The relatively unconstrained atmospheric flight operations enjoyed by space launch providers since the beginning of the space age cannot be taken for granted as a permanent condition.‚Äù55
Range Availability
Launch ranges have limitations in their ability to conduct large numbers of launches. The Eastern and Western ranges can conduct only one launch on any given day and require a day or two between launches to reset. As ranges become congested with multiple launches, delays can accumulate. A launch service provider is typically allowed a couple of launch attempts before having to yield the range to another waiting user, with the delayed launch moving to the next available time slot on the range. After being scrubbed for weather three days in a row, the STS-101 mission was delayed nearly three weeks because Atlas and Delta launches were scheduled for the next two weeks.
The advent of autonomous flight safety systems (AFSS), capable of terminating flight if a rocket malfunctions, is changing this constraint. While only SpaceX is flying such a system today, the Air Force is pressing all U.S. launch service providers to implement AFSS. However, conducting same- day launches may still be problematic because rockets with AFSS use GPS signals, which become disrupted by rocket exhaust plumes.56,57 The separation in time between launches from the same site will need to be sufficient to allow GPS distortions to dissipate, which is analogous to spacing aircraft far enough apart to avoid accidents from shedding vortices. Other considerations include proximity to adjacent launch pads that preclude same-day launch operations or hazardous operations such as static fire testing.
Other factors can hinder the conduct of launch operations on ranges, including workforce limitations and natural disasters. The range operations workforce for CCAFS and VAFB is sized for the expected number of launches and resizing this workforce for a significant increase in launches takes time. Hurricanes, wildfires, and earthquakes may also disrupt operations. A large wildfire in California, for instance, scrubbed an Atlas V launch countdown and caused major damage to the range infrastructure. Launches were halted for seven weeks.
Launch Scrubs
Because launch pads can accommodate only one launch vehicle at a time, launch scrubs contribute to limiting the overall launch throughput. Launch scrubs are exceedingly common and occur for a variety of reasons. The probability of a launch scrub varies somewhat between providers based upon vehicle design, launch commit criteria, and local weather. The time to the next launch attempt after a launch scrub depends on the reason for the scrub. In the case of scrubs for weather, the next attempt can occur on the following day. However, launch scrubs due to flight hardware problems often require a longer time to resolve.58,59
Flight Anomalies
Launch Failures
When rockets fail to place their payload correctly into orbit, a subsequent extensive failure investigation determines the root cause, and corrective action is then taken to prevent a reoccurrence. During the investigation and corrective action period, which may be weeks, months, or years, the entire launch vehicle family is usually grounded. While rare, ascent anomalies can occur on or very near the ground, and the resulting damage to the launch pad can be extensive. Therefore, the availability of that site for future launches depends on the amount of time needed for repairs. The probability of a launch anomaly resulting in a grounding varies among launch vehicles, with some vehicles being perhaps more reliable than others based on their flight history. However, it is unreasonable to assume that any launch vehicle is immune to ascent anomalies.
Satellite Failures
If satellites being deployed fail on orbit, constellation developers may elect to halt deployment until the underlying problem can be determined and corrected. For example, Europe’s initial batch of Galileo satellites experienced problems with their onboard atomic clocks after being placed in orbit. The Galileo managers elected to reschedule an August 2017 launch to December of that year and resolve the problem. 60,61
References (continuation from Part 1)
38 Henry, C. “OneWeb shifts first launch to year‚Äôs end,‚" SpaceNews, May 1, 2018.
39 GAO-15-657, “GPS: Actions Needed to Address Ground System Development Problems and User Equipment Production Readiness,‚Äù September 2015.
40 GAO-18-74, “Global Positioning System: Better Planning and Coordination Needed to Improve Prospects for Fielding Modernized Capability,‚" December 2017.
41 Strong, S., and T. Braden. In Peril: A Daring Decision, a Captain’s Resolve, and the Salvage that Made History, CreateSpace Publishing, 2003.
42 https://spaceflightnow.com/launch-schedule/, accessed March 16, 2018.
43 Foust, J. “Commerce Department pressing ahead with commercial space regulatory reform,‚" SpaceNews, March 5, 2018.
44 Braun, B., and E. Sims. The Aerospace Corporation; “Trespassing on the Final Frontier: Regulatory Challenges for New Space Entrants‚Äù; June 2018.
45 Henry, C. “Arianespace cancels Ariane 5 launch over ISRO satellite issue,‚" SpaceNews, April 24, 2018.
46 Space.com staff. “Boeing‚Äôs Union Strike Delays Satellite Launch Plans, SPACE.com, November 2, 2005.
47 Clark, S. “Launches from Kourou temporarily suspended by social unrest,‚" SpaceNews, March 23, 2017.
48 Aerostar Environmental Services, Inc. “Environmental Assessment for the Operation and Launch of the Falcon 1 and Falcon 9 Space Vehicles at Cape Canaveral Air Force Station, Florida,‚" Orlando, Florida, November 2007.
49 “Final Environmental Assessment for Multi-Use of Launch Complexes 39A and 39B,‚" John F. Kennedy Space Center, Florida, November 1, 2013.
50 “Final Environmental Assessment, Falcon 9 and Falcon 9 Heavy Launch Vehicle Programs from Space Launch Complex 4 East,‚" Vandenberg Air Force Base, California, March 1, 2011.
51 “Final Environmental Impact Statement, SpaceX Texas Launch Site,‚Äù May 2014.
52 “Final Environmental Assessment, Blue Origin Orbital Launch Site at Cape Canaveral Air Force Station, Florida,‚" November 2016.
53 https://www.fema.gov/possible-consequences-not- following-national-environmental-policy-act- process, accessed July 13, 2018.
54 David, L. “How Much Air Pollution Is Produced by Rockets?‚" Scientific American, November 29, 2017.
55 Ross, M., and J. A. Vedda. “The Policy and Science of Rocket Emissions,‚" Center for Space Policy and Strategy, The Aerospace Corporation, April 2018.
56 Calais, E., and J. B. Minster. “GPS, earthquakes, the ionosphere, and the Space Shuttle.‚" Physics of the Earth and Planetary Interiors 105.3-4 (1998): pp. 167-181.
57 Li, G., et al. “Daytime F-region irregularity triggered by rocket-induced ionospheric hole over low latitude.‚" Progress in Earth and Planetary Science 5.1 (2018): p. 11.
58 Cates, G. R. “Space shuttle launch probability analysis: Understanding history so we can predict the future.‚" Aerospace Conference, 2014 IEEE. IEEE, 2014.
59 Cates, G. R., and Kara Schmitt. “The Aerospace launch probability simulation."Aerospace Conference, 2016 IEEE. IEEE, 2016.
60 Amos, J. “Galileo satellites experiencing multiple clock failures," BBC, January 18, 2017.
61 Clark, S. “Four more Galileo navigation satellites ride Ariane 5 rocket into orbit,‚" Spaceflight Now, December 13, 2017.